New TopShim run:

version = topshim 2.0.0
date = 2023-03-23
time = 01:08:47.237
command = topshim 

FINE SHIMMING

Parameters:

probe = Z116098_0188
solvent = CDCl3
shim nucleus = 2H
nucleus optimised for = 13C
o1p (from lock) = 7.24 ppm

Results:


1D Shimming:
Iteration  1: FWHM Before= 2.3 Hz, Target= 0.4 Hz, After= 0.5 Hz
Iteration  2: FWHM Before= 0.5 Hz, Target= 0.2 Hz, After= 0.6 Hz
Iteration  3: FWHM Before= 0.6 Hz, Target= 0.3 Hz, After= 0.5 Hz
Iteration  4: FWHM Before= 0.5 Hz, Target= 0.3 Hz, After= 0.4 Hz
Iteration  5: FWHM Before= 0.4 Hz, Target= 0.4 Hz
Shim succeeded

Lineshape quality factor (1D spectrum, spinning) = 0.629

shim changes: 
Z	-158
Z2	-54
Z3	+20
Z4	+272
Z5	-283

duration = 1 min 39 sec
completed successfully
finished Thu Mar 23 01:10:24 2023


========================================================================